Renovations: Difference between revisions

Jump to navigation Jump to search
1,911 bytes added ,  11 August
Added the costs of renovations for the yard (WIP)
m (Fixed a few spelling mistakes)
(Added the costs of renovations for the yard (WIP))
Line 19: Line 19:


Resources needed for renovations can be placed in the "Renovation Resources" chest located next to the contractor, it is wise to plan ahead and buy or find rarer resources in advance, as their availably might be low when a time for renovation comes otherwise. Samuel Jonasson also accepts stolen resources for the renovations.
Resources needed for renovations can be placed in the "Renovation Resources" chest located next to the contractor, it is wise to plan ahead and buy or find rarer resources in advance, as their availably might be low when a time for renovation comes otherwise. Samuel Jonasson also accepts stolen resources for the renovations.
== Renovation Costs : ==
=== Yard : ===
{| class="wikitable sortable mw-collapsible mw-collapsed"
|+COURTYARD
!Level
!Dependencies
!Cost (OC)
!Cost (Materials)
!Cost (RM)
|-
|I
|
|6.800
|Planks x40
Nails x80
|700
|-
|II
|
|13.000
|Planks x40
Nails x80
Sand x5
Cement x4
Tarp x1
Mesh x1
Wire x1
|1.100
|-
|III
|
|60.000
|Planks x20
Nails x40
Sheet Metal x10
Cement x8
Fertile Soil x5
Wire x5
Brick x20
|10.000
|-
|IV
|
|100.000
|Planks x40
Nails x40
Sheet Metal x12
Cement x16
Bucket of paint x4
Wire x10
Wiring Components x5
Brick x25
|30.000
|-
|V
|
|''Not Implemented''
|''Not Implemented''
|''Not Implemented''
|}
{| class="wikitable sortable mw-collapsible mw-collapsed"
|+FACADE
!Level
!Dependencies
!Cost (OC)
!Cost (Materials)
!Cost (RM)
|-
|I
|
|7.000
|Cement x10
Scrap metal x10
|800
|-
|II
|Facade I
|14.500
|Cement x15
Scrap metal x15
Planks x3
Asbestos x5
|1.700
|-
|III
|Facade II
|40.000
|Cement x20
Scrap metal x20
Asbestos x15
|10.000
|-
|IV
|Facade III
|100.000
|Cement x20
Scrap metal x30
Bucket of paint x15
Insulation wool x15
|20.000
|-
|V
|
|''Not Implemented''
|''Not Implemented''
|''Not Implemented''
|}
{| class="wikitable sortable mw-collapsible mw-collapsed"
|+
SAUNA & PIER
!Upgrade
!Level
!Cost (OC)
!Cost (Materials)
!Cost (RM)
|-
|Courtyard
|I
|15.000
|Planks x40
Nails x80
Leather roll x1
Scrap metal x20
Pipe x2
Duct tape x4
Sheet Metal x4
Bucket of paint x1
Rock x4
|800
|-
|
|II
|21.500
|Planks x60
Nails x120
Cloth roll x1
Scrap metal x30
Pipe x3
Duct tape x8
Sheet Metal x4
|1.700
|-
|
|III
|60.000
|Planks x30
Nails x80
Cloth roll x2
Scrap metal x20
Pipe x6
Duct tape x2
Sheet Metal x8
Cement x4
Glass Pane x4
Bucket of paint x3
|10.000
|-
|
|IV
|60.000
|Planks x60
Nails x160
Cloth roll x2
Scrap metal x30
Pipe x6
Duct tape x2
Sheet Metal x8
Cement x2
Glass Pane x6
Bucket of paint x6
|20.000
|-
|
|V
|''Not Implemented''
|''Not Implemented''
|''Not Implemented''
|}


==See also==
==See also==
10

edits